Current regeneration projects in Ruthin
			The following projects have secured funding and either under construction or in development, preparing for construction.
			
			Welfare improvements to Lôn Parcwr Depot
			Project overview: Temporary health and safety and welfare improvements.
			Funding: Denbighshire County Council Capital 
			Project value: £175,000
			
			
			Salt storage facilities
			Project overview: Procurement of a new salt barn.
			Funding: Denbighshire County Council Capital 
			Project value: £1,300,000
			Timescales: Tender upcoming
			
			Gwyddelwern - Community Hall
			Project overview: A new community hall facility in Gwyddelwern, proposed to be located on the site of Ysgol Bro Elwern. Funding has been awarded and initial designs have progressed for the scheme.
			Funding: UK Government Levelling Up Fund
			Project value: £1,400,000
			Timescales: March 2026
			
			Bryneglwys scheme
			Project overview: New community facilities in Bryneglwys.
			Funding: UK Levelling Up Fund
			Project value: £392,000
			Timescales: March 2026
			
			Ruthin Clock Tower
			Project overview: Renovation of clock tower exterior.
			Funding: UK Government Levelling Up Fund
			Project value: £200,000
			Timescales: March 2026
			
			St Peter's Square 
			Project overview: Traffic works relating to the roundabout, traffic calming and associated public realm around the Square.
			Funding: UK Government Levelling Up Fund
			Project value: £3,000,000
			Timescales: March 2026
			
			The Old Cloisters
			Project overview: Fully restore and refurbish the old Cloisters. To also provide a community-franchised dining experience.
			Funding: UK Government Levelling Up Fund
			Project value: £800,000
			Timescales: March 2026
			
			St Peter's Church
			Project overview: Access improvements into the Church and improving the visitor experience (level floor, replace heating, enable large indoor activities). Bilingual signs.
			Funding: UK Government Levelling Up Fund
			Project value: £700,000
			Timescales: March 2026
			
			Nant Clwyd-y-Dre
			Project overview: Refurbish the derelict Grade I listed west wing into holiday accommodation and structural repair of the two-storey gazebo. 
			Funding: UK Government Levelling Up Fund
			Project value: £500,000
			Timescales: March 2026
			
			Cae Ddol
			Project overview: New pathways, modern play park, improved entrance and connect with the Heritage theme.
			Funding: UK Government Levelling Up Fund
			Project value: £500,000
			Timescales: March 2026
			
			Gaol/46 Clwyd Street
			Project overview: New entrance to the Gaol via 46 Clwyd St, a museum shop, a café and space for changing exhibitions as well as a new interpretation of the munitions shed.
			Funding: UK Government Levelling Up Fund
			Project value: £300,000
			Timescales: March 2026