Levelling Up Fund Round 2: Programme Delivery Plan

Information about the Levelling Up Fund Round 2 project's programme delivery plans.
Delivery plan key milestones
All delivery plan milestones are provisional and are based on best information at this stage in the project’s development.
This information will be updated if information changes.
Select one of the following projects to view it's delivery plan key milestones:
St Peter's Square
St Peter’s Square Programme Delivery Plan
| Key Milestone |
Date |
| Consultation and engagement |
Completed |
| Detailed designs available |
Completed |
| Traffic Regulation Order submitted |
November 2025 |
| Procurement start |
October / November 2025 |
| Construction start |
February 2026 |
| Handover |
November 2026 |
St Peter's Church and Cloisters
St Peter's Church and Cloisters Programme Delivery Plan
| Key Milestone |
Date |
| Procurement start |
Completed |
| Construction start |
Commenced |
| Construction Finish / Handover |
March 2026 |
Ruthin Clock Tower
Ruthin Clock Tower Programme Delivery Plan
| Key Milestone |
Date |
| Procurement start |
Completed July 2024 |
| Consultation and engagement |
Completed April/May 2024 |
| Construction start |
August 2024 |
| Construction finish / Handover |
Completed December 2024 |
Ruthin Gaol/46 Clwyd Street
Ruthin Gaol/46 Clwyd Street Programme Delivery Plan
| Key Milestone |
Date |
| Detailed designs available |
Completed May 2024 |
| Planning application submitted |
Completed |
| Procurement start |
Completed |
| Construction start |
Commenced |
| Construction finish / Handover |
January 2026 |
Ruthin Nantclwyd y Dre
Ruthin Nantclwyd y Dre Programme Delivery Plan
| Key Milestone |
Date |
| Planning application submitted |
Completed |
| Procurement Start |
Completed |
| Construction start |
Commenced |
| Construction finish / Handover |
May 2026 |
Ruthin Cae Ddol
Ruthin Cae Ddol Programme Delivery Plan
| Key Milestone |
Date |
| Consultation and engagement |
Completed |
| Planning application submitted |
Submitted November 2025 |
| Construction Start |
April 2026 |
| Construction finish / Handover |
August 2026 |
Moel Famau Facilities and Cycle Paths
Moel Famau Facilities and Cycle Paths Programme Delivery Plan
| Key Milestone |
Date |
| Consultation and engagement |
Completed |
| Planning application submitted |
Completed |
| Procurement start |
Under review |
| Construction start |
Under review |
| Construction finish / Handover |
Under review |
Loggerheads Building and External
Loggerheads Building and External Programme Delivery Plan
| Key Milestone |
Date |
| Consultation and engagement |
Completed |
| Planning Application and FRAP Consent App Submitted |
Completed |
| Procurement start |
Completed |
| Construction start |
Commenced |
| Construction finish / Handover |
March 2026 |
Bryneglwys School - Community Hub
Bryneglwys School - Community Hub Programme Delivery Plan
| Key Milestone |
Date |
| Procurement start |
Completed |
| Construction start |
Completed |
| Handover |
Completed |
Gwyddelwern - Community Hub
Gwyddelwern - Community Hub Programme Delivery Plan
| Key Milestone |
Date |
| Planning application Submitted |
Completed |
| SAB application submission |
Completed |
| Procurement start |
Commenced |
| Construction start |
January 2026 |
| Construction finish / Handover |
October 2026 |