Levelling Up Fund Round 2: Programme Delivery Plan

Funded by UK Government logo

Information about the Levelling Up Fund Round 2 project's programme delivery plans.

Delivery plan key milestones

All delivery plan milestones are provisional and are based on best information at this stage in the project’s development. 

This information will be updated if information changes.

Select one of the following projects to view it's delivery plan key milestones:

St Peter's Square
St Peter’s Square Programme Delivery Plan
Key Milestone Date 
Consultation and engagement March/April/May 2024
Detailed designs available March/April 2024
Traffic Regulation Order submitted September/October/November 2024
Procurement start December 2024
Construction start September 2025
Handover February 2026
St Peter's Church and Cloisters
St Peter's Church and Cloisters Programme Delivery Plan
Key Milestone Date 
Procurement start February 2024
Construction start April 2024
Construction Finish / Handover March/April 2025
Ruthin Clock Tower
Ruthin Clock Tower Programme Delivery Plan
Key Milestone Date 
Procurement start February/March 2024
Consultation and engagement March/April/May 2024
Construction start June 2024
Construction finish / Handover October/November 24
Ruthin Gaol/46 Clwyd Street
Ruthin Gaol/46 Clwyd Street Programme Delivery Plan
Key Milestone Date 
Detailed designs available March/April 2024
Planning application submitted March/April 2024
Procurement start August/September 2024
Construction start November 2024
Construction finish / Handover May/June 2025
Ruthin Nantclwyd y Dre
Ruthin Nantclwyd y Dre Programme Delivery Plan
Key Milestone Date 
Planning application submitted March/April 2024
Procurement Start July / August 24
Construction start November 2024
Construction finish / Handover July/August 2025
Ruthin Cae Ddol
Ruthin Cae Ddol Programme Delivery Plan
Key Milestone Date 
Consultation and engagement March/April/May 2024
Planning Application Submitted October 2024
Construction Start September 2025
Construction finish / Handover February 2026
Moel Famau Facilities and Cycle Paths
Moel Famau Facilities and Cycle Paths Programme Delivery Plan
Key Milestone Date 
Consultation and engagement February/March 2024
Planning application submitted April/June 2024
Procurement start August/September 2024
Construction start December 2024
Construction finish / Handover June 2025
Loggerheads Building and External
Loggerheads Building and External Programme Delivery Plan
Key Milestone Date 
Consultation and engagement February/March 2024
Planning Application and FRAP Consent App Submitted April 2024/September 2024
Procurement start August/September 2024
Construction start December 2024
Construction finish / Handover June 2025
Bryneglwys School - Community Hub
Bryneglwys School - Community Hub Programme Delivery Plan
Key Milestone Date 
Procurement start February 2024
Construction start April 2024
Handover September 2024
Gwyddelwern - Community Hub
Gwyddelwern - Community Hub Programme Delivery Plan
Key Milestone Date 
Pre-planning consultation March 2024
Planning application Submitted April/June 2024
SAB application submission April/July 2024
Procurement start November 2024
Construction start March 2025
Construction finish / Handover December 2025