Levelling Up Fund Round 2: Programme Delivery Plan

Funded by UK Government logo

Information about the Levelling Up Fund Round 2 project's programme delivery plans.

Delivery plan key milestones

All delivery plan milestones are provisional and are based on best information at this stage in the project’s development. 

This information will be updated if information changes.

Select one of the following projects to view it's delivery plan key milestones:

St Peter's Square
St Peter’s Square Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Completed
Detailed designs available Completed
Traffic Regulation Order submitted November 2025
Procurement start October / November 2025
Construction start February 2026
Handover November 2026
St Peter's Church and Cloisters
St Peter's Church and Cloisters Programme Delivery Plan
Key Milestone Date 
Procurement start Completed
Construction start Commenced
Construction Finish / Handover March 2026
Ruthin Clock Tower
Ruthin Clock Tower Programme Delivery Plan
Key Milestone Date 
Procurement start Completed July 2024
Consultation and engagement Completed April/May 2024
Construction start August 2024
Construction finish / Handover Completed December 2024
Ruthin Gaol/46 Clwyd Street
Ruthin Gaol/46 Clwyd Street Programme Delivery Plan
Key Milestone Date 
Detailed designs available Completed May 2024
Planning application submitted Completed
Procurement start Completed
Construction start Commenced
Construction finish / Handover January 2026
Ruthin Nantclwyd y Dre
Ruthin Nantclwyd y Dre Programme Delivery Plan
Key Milestone Date 
Planning application submitted Completed
Procurement Start Completed
Construction start Commenced
Construction finish / Handover May 2026
Ruthin Cae Ddol
Ruthin Cae Ddol Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Completed
Planning application submitted Submitted November 2025
Construction Start April 2026
Construction finish / Handover August 2026
Moel Famau Facilities and Cycle Paths
Moel Famau Facilities and Cycle Paths Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Completed
Planning application submitted Completed
Procurement start Under review
Construction start Under review
Construction finish / Handover Under review
Loggerheads Building and External
Loggerheads Building and External Programme Delivery Plan
Key Milestone Date 
Consultation and engagement Completed
Planning Application and FRAP Consent App Submitted Completed
Procurement start Completed
Construction start Commenced
Construction finish / Handover March 2026
Bryneglwys School - Community Hub
Bryneglwys School - Community Hub Programme Delivery Plan
Key Milestone Date 
Procurement start Completed
Construction start Completed
Handover Completed
Gwyddelwern - Community Hub
Gwyddelwern - Community Hub Programme Delivery Plan
Key Milestone Date 
Planning application Submitted Completed
SAB application submission Completed
Procurement start Commenced
Construction start January 2026
Construction finish / Handover October 2026